Alessandro Boulevard Improvements

Riverside, CA

Client: Black & Veatch

 

Alessandro Boulevard

 

The City of Riverside required street improvement mitigation measures to Allessandro Boulevard as part of the Metropolitan Water District (MWD) water transmission pipeline installation project. The street improvements included temporary and permanent improvements to 2-miles of Alessandro Boulevard from Mission Grove Parkway to Sycamore Canyon. The project was completed in two phases. The project added a new lane in both directions.

Phase 1 included widening of the roadway to provide traffic handling during the pipeline construction. Traffic was diverted to the southerly (eastbound) portion of the road. Temporary improvements included median removal and paving, curb removal and paving, traffic signal modifications (at four locations), irrigation system modifications, and slope grading.

Phase 2 included restoring the roadway pavement sections, widening the roadway to provide three travel lanes in each direction, installation of raised center medians, drainage installations and modification, traffic signal modifications, and irrigation system improvements. 

 